K-IV cost escalates by whopping 600pc due to delay, rupee fall
ISLAMABAD - The cost of the Greater Karachi Bulk Water Supply Scheme (K-IV) has escalated by almost 600 percent from the originally approved Rs25.552 billion to Rs171.714 billion, mainly due to delay in the execution of the project and depreciation of Pakistani rupee. While the project’s completion timeline has increased from 84 months (till July 2021 in the original PC-1) to 161 months (till December 2027 in the second revised PC-I), official source told The Nation.