Two CAREC-II road packages reach 82% completion
ISLAMABAD, July 30 (INP-Wealth Pakistan) -- Two major N-55 dualization packages have entered the final stretch, with physical progress reaching 82% on the Kashmore-Rojhan section and 79% on the Rojhan-Rajanpur section ahead of their scheduled completion dates in October 2026.