The National Accountability Bureau (NAB) has formally launched an inquiry into alleged procurement irregularities involving the Power Division, National Grid Company (NGC) and other officials in two major power transmission projects,

Business Recorder

reported, citing sources.

The investigation covers the 765kV Dasu-Islamabad Transmission Line Project (Lot-IV) and the ADB-40 IB-2022 Lot II-A contract involving ACSR Bunting Conductors, following a reference from the Senate Standing Committee on Economic Affairs under the National Accountability Ordinance, 1999.

In a letter issued by NAB Additional Director Sajid Ali on behalf of the director general, the bureau sought the Power Division’s response to allegations and observations raised by the parliamentary committee, along with attested copies of all previous inquiries and fact-finding reports concerning the two projects.

A key issue raised by the Senate committee, headed by Senator Saif Ullah Abro, concerns an alleged irregular payment of Rs1.282 billion in taxes to a contractor associated with the 765kV Islamabad West Grid Station project.

Abro maintained that the contract stipulated that quoted rates were inclusive of all taxes and that the department had previously acknowledged the irregular payment. He also highlighted a difference of approximately Rs9 billion between the bids submitted by the lowest and next-highest bidders.

The committee chairman called for the recovery of Rs1.282 billion from the contractor and questioned the failure of NGC management to implement the committee’s earlier recommendations despite assurances of action.

He also accused the Deputy Managing Director of NTDC of misleading the parliamentary committee while presenting findings from an internal review of previous inquiries, contract documents and tax-related issues.

Audit officials informed the committee that objections had been raised during the certification of the foreign-funded project and subsequently discussed at Departmental Accounts Committee (DAC) meetings in September 2025.

Director General Audit (Power) Ayesha Siddique disputed an earlier claim by Power Division officials that a special audit had been conducted and the tax matter settled by the DAC.

She explained that the Auditor General had identified a material deviation during the certification exercise, while the DAC had expressed reservations over the department’s position. The matter would ultimately be considered by the Public Accounts Committee (PAC).

The Auditor General’s compliance audit would also examine project activities, contract management and the confidential inquiry committee.

Referring to Clauses 3.25 and 3.26 of the World Bank’s procurement regulations, Abro stressed that responsibility for the procurement process rested with the borrower.

The committee chairman rejected a proposal by the Special Secretary, Power Division, to conduct another internal inquiry, instead recommending that the Economic Affairs Division (EAD) refer the matter to the Federal Investigation Agency (FIA) and NAB.

The Senate committee had also unanimously decided to visit the Dasu-Islamabad Transmission Line Project in April 2026 to assess its progress and examine outstanding issues.

Separately, the parliamentary committee had sought details of disciplinary action against NESPAK officials allegedly involved in procurement irregularities concerning the ACSR Bunting Conductor contract.

It expressed displeasure over the absence of the Power Division secretary, directed the ministry to submit a detailed report on action taken against the officials concerned, and instructed the EAD to ensure the secretary’s attendance at its next meeting.

The committee had also recommended referring the conductor procurement case to the FIA and NAB over alleged violations of procurement rules.