Image for: Construction advances on 208km Indus Highway project

 

By Abdul Ghani


ISLAMABAD, Nov. 26 (INP-Wealth Pakistan) -- Construction activities on the 208.19-kilometre Dera Ghazi Khan-Dera Ismail Khan section of the Indus Highway (N-55) are progressing, with contractors mobilising 143 units of highway and structural machinery under the CAREC Tranche-III project.


According to documents available with Wealth Pakistan, the machinery deployment includes 107 units of highway construction equipment and 36 units of structural machinery and equipment, positioned at contractor camps and available stretches along the project corridor.


The Rs94.60 billion project involves the dualization and upgrading of the D.G. Khan-D.I. Khan section and has been divided into two packages. Lot-3 covers 112 kilometres from DG Khan to Tibbi Qaisrani, while Lot-4 spans 96 kilometres from Tibbi Qaisrani to DI Khan.


The contract for Lot-3 is worth Rs51.99 billion, while Lot-4 carries a contract cost of Rs42.60 billion. Both contracts have been awarded to joint ventures involving China's Ningxia Communication Construction Company, Dynamic Constructors, and Rustam Associates.


According to the progress report, construction commenced on July 6, 2026, with completion scheduled for July 5, 2028.


The contractors have received mobilisation advances of Rs5.194 billion for Lot-3 and Rs4.255 billion for Lot-4, taking the combined amount to approximately Rs9.45 billion.


The report shows that contractor camps have been established at three locations under Lot-3 and one location under Lot-4. Installation of batching plants, centre lines and cross-section marking, soil investigations, earthwork, and structural activities are also underway.


Progress has also been recorded in bridge construction investigations. Under Lot-3, confirmatory boring and soil investigations have been completed at 26 out of 32 locations, while 10 out of 16 investigations have been completed under Lot-4.


Land clearing and grubbing activities in areas covered by the Land Acquisition and Resettlement Plan (LARP) have been completed over 35 kilometres under Lot-3 and five kilometres under Lot-4, bringing the combined length to 40 kilometres.


The deployed highway machinery includes dumpers, graders, front-end loaders, plain rollers, sheepsfoot rollers, water tank bowsers, excavators, bulldozers, asphalt plants, vibratory rollers and pavers. Structural equipment includes concrete batching plants, concrete pumps, transit mixers, lift cranes, jackhammers, plate compactors, generators and tower lights.


Meanwhile, the remaining 121.5-kilometre Rajanpur-DG Khan section of the broader 330-kilometre Indus Highway expansion project has been divided into two packages: Rajanpur-Jampur (57.5 kilometres) and Jampur-DG Khan (64 kilometres).


The two packages have a combined PC-I cost of Rs63.15 billion. Letters of acceptance have been issued, while their final Land Acquisition and Resettlement Plans have been submitted to the Asian Development Bank (ADB) for approval after addressing its observations.


The contract award process for the two packages is expected to be completed by December 2026, subject to ADB approval.