Image for: NHA advances procurement of contract for $93.78m Chitral road

 

By Abdul Ghani 


ISLAMABAD, Nov. 26 (INP-Wealth Pakistan) -- The National Highway Authority (NHA) is moving forward with contractor selection for the $93.78 million National Highway N-45 (Kalkatak-Chitral) Section-III project, as it has shared the technical bid evaluation with the development partner, marking progress toward implementation of the 48-kilometre road scheme.


According to a document available with Wealth Pakistan, the Export-Import Bank of Korea is financing the project, which aims to improve regional connectivity by modernising transportation infrastructure.


The document shows that the project has a total financing commitment of $93.78 million. Against this commitment, $1.17 million has so far been disbursed, while the remaining $92.61 million is yet to be disbursed.


The project has been allocated an estimated budget of $1.55 million for the fiscal year 2026-27. However, no disbursement has been recorded against the project during the current fiscal year.


The loan agreement was signed on September 23, 2016, following approval of its PC-I on August 9, 2016. The original loan closing date of March 19, 2021, was subsequently extended to August 30, 2025.


To facilitate further progress, the request for an extension of the project loan is currently pending with the NHA and the Ministry of Communications.


The NHA has been asked to expedite approval of the loan extension so that the matter can be forwarded to Korea's EXIM Bank for consideration.


Once implemented, the 48-kilometre road project is expected to contribute to improved transportation infrastructure and regional connectivity along the Kalkatak-Chitral section of N-45.