By Ijaz Kakakhel
ISLAMABAD, Nov. 26 (INP-Wealth Pakistan) -- The French Development Agency (AFD) has committed €479.7 million for eight major power projects, with approximately €188.46 million already disbursed against the total commitments.
Spread across Azad Jammu and Kashmir (AJK), Khyber Pakhtunkhwa, Gilgit-Baltistan and Punjab, the projects are being implemented through the Water and Power Development Authority (WAPDA), the AJK government, and the National Grid Company (NGC). The financing comprises seven loan agreements of €479.5 million and a grant of €0.2 million, according to the project status report, a copy of which is available with Wealth Pakistan.
Among the major initiatives is the 48-megawatt Jagran-II Hydropower Project in AJK, for which AFD committed €68 million. The project has achieved 93 per cent physical progress, while €61.29 million, or 92 per cent, of the committed financing has been disbursed. However, the loan agreement will expire in December 2026, requiring the Ministry of Economic Affairs (MoEA) to consider an extension if necessary.
The Harpo Hydropower Project in Gilgit-Baltistan, backed by a €50 million AFD loan, has achieved 32.25 per cent physical progress, while financial disbursement stands at €0.38 million, or 0.76 per cent of the total amount.
WAPDA has requested an extension of the loan agreement, and the proposal has been forwarded to the Ministry of Water Resources (MoWR) for further processing and submission to AFD for consideration.
Similarly, the Warsak Hydropower Project in Khyber Pakhtunkhwa, involving €41.5 million in AFD financing, has recorded 65 per cent physical progress and €32.64 million in financial disbursement. However, the project faces implementation delays, with its original implementation period having expired. A revised PC-I is also under process.
The refurbishment and upgradation of generating units at Mangla Power Station in AJK, supported by a €90 million loan, has achieved approximately 74.96 per cent physical progress, with €69.42 million disbursed, representing 77 per cent of the committed amount. An extension request was submitted to AFD in January 2026.
AFD is also financing the €35 million Dargai Rehabilitation Hydropower Project and the €15 million Chitral Power Station capacity enhancement project in Khyber Pakhtunkhwa. The Chitral project aims to increase the station's generation capacity from 1MW to 5MW. Both initiatives involve revised subsidiary loan agreements requiring completion of formalities and signatures.
Another major component is the €180 million NTDC Grid and Transmission Lines Project, covering Sialkot, Arifwala and Vehari in Punjab. The project is currently at the material procurement stage, with €21.51 million, or 13 per cent, disbursed. Authorities are pursuing approval of a fresh PC-I based on anticipated project savings.
In addition, AFD has provided a €0.2 million grant for the Dargai Rehabilitation and Chitral Capacity Enhancement Hydropower Project.
Separately, the agency has extended a €0.5 million grant for technical assistance to the Private Power and Infrastructure Board (PPIB), with 70 per cent physical progress reported.
Despite substantial financial commitments, several projects face administrative and implementation challenges, particularly with loan extensions, revised project approvals, and subsidiary loan agreements. Timely resolution of these issues, along with improved coordination between executing agencies and government departments, will be critical to accelerating implementation.