ISLAMABAD - The federal government is targeting March 2028 for the 969MW Neelum-Jhelum Hydropower Project to resume power generation as work has begun to revive the project shut for over two years, officials said on Thursday. The disclosure was made by the official of the Independent Systems and Market Operator (ISMO) in a public hearing conducted by NEPRA on the CPPA-G petition seeking a Rs2.88 per unit increase in tariff as fuel charges adjustment for October 2026.

The project, built at a cost of over Rs500 billion, has been closed for more than two years after its tunnel collapsed in April 2024. In a reply regarding the restart of Neelum Jhelum work, the ISMO official said that work has already begun and they are expecting to complete work on NJHPP by March 2028. NEPRA has completed the hearing on the petition. CPPA-G had sought the increase for October FCA, which would have placed a total burden of around Rs 30 billion on consumers. According the CPPA-G, the fuel cost remained at Rs10.75 per unit against the reference of Rs7.87 per unit during the month. During the hearing, the Power Division informed NEPRA that the government is sending policy guidelines to keep the FCA stable from October to December, so that the increase is limited to Rs0.83 per unit every month from October to December. NEPRA will now issue its decision on the October adjustment in accordance with the government’s policy guidelines. The hearing was told that hydropower generation fell by 500 million units in October, while expensive fuel prices, including LNG, pushed up the cost of power generation.

Official said that Pakistan’s power generation pattern has changed sharply since 2022, with a deep midday dip and a sharp evening surge. Data presented during the hearing showed that on 1st Oct, 2026, generation started at 18,622MW at 1am, crashed to 12,683MW at 1pm, and then surged back to 18,252MW at 9pm. In comparison, on 2nd Oct, 2022, generation remained almost flat throughout the day, starting at 17,075MW, dipping only to 15,231MW in the morning, and peaking at 17,858 MW in the evening. Official said the deep midday dip in 2026 reflects the rapid growth of rooftop solar, which takes load off the national grid during the day and forces the grid to pick up the entire load again in the evening when solar generation stops. Official of the Power Division said year-on-year average generation in October 2026 was also higher than October 2025 at every hour, with the evening peak rising to 16,573MW at 5PM in October 2026 from 15,324MW in October 2025.