The National Grid Company of Pakistan Limited (NGC) has held Chinese contractor Sinohydro Corporation Limited responsible for delays of 14 to 16 months in key activities relating to the construction of a 765kV transmission line connecting the 4,320MW Dasu Hydropower Project to Mansehra Grid Station,
Business Recorder
reported.
Responding on November 16 to a letter sent by Sinohydro on November 2, 2026, NGC rejected the contractor’s allegations that pending payments, engineering approvals, right-of-way constraints and statutory clearances were responsible for slow project execution.
NGC cited several missed contractual milestones, including the route survey and revalidation, which was completed in August 2024 instead of June 2023, and designs for D7N and D7H transmission towers, which were finalised in March 2025 against a November 2023 deadline.
Pile foundation designs originally due in October 2023 remained under consideration, with the latest document approved on November 10, 2026. Prototype tower load testing, scheduled for December 2023, also faced significant delays, with retesting of D7N and D7T towers concluding in April 2025 and May 2026, respectively.
NGC maintained that these activities were within the contractor’s control and independent of right-of-way availability.
The company claimed that between 20 and 25 work fronts remained available to Sinohydro at any given time, but many were left unutilised due to shortages of subcontractors, tower stubs and approved designs. At more than 100 locations, right-of-way clearance was allegedly never attempted because of inadequate resource mobilisation.
On financial matters, NGC said payments were contractually subject to the measurement and certification of completed work, adding that legitimate claims were being processed while disputed or unapproved amounts could not be classified as delayed payments.
The company also maintained that access-road construction and obtaining forest and National Highway Authority clearances were primarily the contractor’s responsibility, with NGC required to facilitate the latter.
Engineering disagreements included incomplete technical submissions and insufficient justification for proposed dry-pile foundations at approximately 104 locations.
NGC said the project consultant had developed engineering solutions for additional leg extensions of D7M and D7L towers to facilitate construction. Sinohydro has been given 14 days to adopt the proposed designs or communicate specific technical reservations.
The company further alleged that Sinohydro had failed to make its design team available in Pakistan during an expert mission conducted by the consultant from September 9 to 17, 2026, to resolve outstanding engineering issues.
NGC maintained that Sinohydro’s November 2 correspondence did not meet contractual requirements for a formal claim and reserved its right to reject claims submitted outside the prescribed timeframe.
The contract covers the design, supply, installation, testing and commissioning of the 765kV double-circuit transmission line under Lot-I of the Dasu power evacuation project.