The National Electric Power Regulatory Authority (NEPRA) has questioned Medrian Energy Limited, HNDS Energy Limited and Helios Power Limited, sponsors of three 50MWp solar power projects, over their separate petitions seeking modifications to tariff determinations issued on February 21, 2020, under which a levelised tariff of Rs5.6988 per kWh (US cents 3.6684 per kWh) was approved, raising concerns about the potential financial implications of construction delays for electricity consumers,
Business Recorder
reported.
The companies have sought revisions concerning the Commercial Operation Date (COD), Interest During Construction (IDC) and Return on Equity During Construction (ROEDC).
The petitioners have requested that the maximum permitted construction period of ten months commence from the Construction Start Date (CSD) of June 14, 2022, as stipulated in the Energy Purchase Agreement (EPA), instead of the Financial Close (FC) date of February 19, 2021.
They have also sought calculation of IDC at COD based on actual debt drawdowns during the revised ten-month construction period, within the overall debt approved by NEPRA.
Similarly, the companies have requested adjustments to ROEDC based on actual equity injections during the same period, subject to the approved equity limits, alongside a day-for-day extension of the permitted construction period to account for force majeure events.
During the hearing, NEPRA members Amina Ahmed, Maqsood Anwar Khan and Ghulamullah Shaikh questioned representatives of the project sponsors and the Central Power Purchasing Agency-Guarantee (CPPA-G) about the justification for the requested relief and its potential impact on consumers.
The sponsors attributed construction delays to difficulties in land acquisition and other project-related issues, arguing that the entire feasibility study had to be revised because of problems securing the proposed sites. They maintained that similar relief had previously been granted to certain other power companies.
However, CPPA-G maintained that it had taken measures to prevent the financial burden arising from project delays from being transferred to electricity consumers.
Its representative explained that the companies had initially approached the Alternative Energy Development Board (AEDB) and the Sindh government, citing events of default and force majeure circumstances, which prevented CPPA-G from issuing termination notices until those matters were resolved.
The agency subsequently issued termination notices after the outstanding issues with AEDB and the provincial government were addressed.
NEPRA Member (Law) Ghulamullah Shaikh questioned whether the original tariff determinations had explicitly established that construction delays would not carry financial implications for consumers.
A representative of the project companies acknowledged that the wording of the original determinations supported the regulator's interpretation but maintained that construction could not commence because the companies lacked possession of the required project sites.