By Ijaz Kakakhel
ISLAMABAD, Nov 24 (INP-Wealth Pakistan) -- Pakistan is implementing four development projects worth approximately $90.9 million with financial assistance from the Japan International Cooperation Agency (JICA), including three grant-funded schemes and one loan-funded project, with completion timelines extending from 2027 to 2030.
According to official documents available with Wealth Pakistan, the projects cover weather surveillance, flood management and electricity transmission infrastructure, reflecting Japan's continued support for Pakistan's disaster preparedness and infrastructure development.
Of the total financial commitments, approximately $66.9 million has been allocated as grants for three projects, while $24 million has been committed as a loan for an electricity transmission project.
The first project relates to installing a weather surveillance radar in Multan, with a committed Japanese grant of $23.98 million. The agreement was signed on August 31, 2018, and the project is scheduled for completion by March 31, 2027.
Executed under the Defence Division, the project has achieved 12 per cent financial progress. The project is proceeding smoothly.
The second project involves installing a weather surveillance radar in Sukkur, with a Japanese grant commitment of $24.4 million. The agreement was signed on January 25, 2021, and the project is expected to be completed by December 31, 2027.
The government is also contributing Rs370.813 million to the Sukkur project, while Japanese grant assistance amounts to Rs5,354.2 million.
Despite its scheduled completion in 2027, the project has registered financial progress of only 0.18 per cent.
The third grant-funded initiative, titled "Flood Management Enhancement in the Indus Basin”, carries a Japanese commitment of $18.5 million.
The agreement was signed on November 13, 2024, and the project is scheduled for completion by December 31, 2030. The Federal Flood Commission is executing the project under the water sector.
The project has recorded financial progress of 0.94 per cent, although its implementation status has been reported as satisfactory.
Meanwhile, the fourth initiative is the 220kV Islamabad-Burhan Transmission Line Project, Phase-I, financed through a $24 million Japanese loan.
The loan agreement was signed on May 4, 2017, and the project's completion deadline has been set for September 30, 2030.
National Grid Company is implementing the project under the Power Division. Its reported financial progress stands at 3.92 per cent, with authorities reporting that work is progressing smoothly.
The projects are expected to strengthen Pakistan's weather monitoring capabilities, flood management infrastructure and electricity transmission network.