A breakdown of the sole coal-handling conveyor at Pakistan International Bulk Terminal (PIBT) at Port Qasim has disrupted imported coal supplies since November 18, threatening electricity generation and industrial operations while exposing power producers and suppliers to mounting financial losses.

Dawn

reported that the disruption comes amid existing LNG supply constraints and reduced hydroelectric power availability, affecting coal supplies to power plants, cement manufacturers and textile industries.

Coal unloading capacity at the terminal has fallen by 90%, from 30,000 tonnes to 3,000 tonnes per day, as cargo is being discharged through conventional methods.

State-owned Jamshoro Power Company (JPC) has warned that delays involving its five upcoming vessels could result in demurrage charges exceeding an estimated $2–3 million (Rs556–834 million), alongside potential capacity payment losses of approximately Rs2.2 billion per month due to insufficient coal inventories.

In a letter to PIBT and the federal government, JPC warned that delayed shipments could compromise electricity generation, increase port congestion and raise future coal procurement and power generation costs.

PIBT attributed the conveyor damage to excessive dust and foreign materials, particularly sharp iron pieces, in a shipment of Tanzanian coal being unloaded from the vessel Pegasus 8 on November 18. The terminal operator estimated that repairs could take eight to 10 days.

JPC has demanded that PIBT declare force majeure, holding the terminal operator responsible for demurrage, detention charges and other financial losses arising from the disruption.

Power producers and coal suppliers have also sought a force majeure declaration to facilitate insurance claims and limit their financial exposure.

However, PIBT has rejected these requests on the grounds that cargo unloading operations are continuing through alternative methods, albeit at significantly reduced rates.

A shipping line has also warned that it would seek compensation for prolonged unloading delays and any damage sustained by its vessel during conventional cargo handling.

The disruption has highlighted PIBT's dependence on a single jetty, coal berth and conveyor system. A second conveyor proposed in 2021 to increase annual coal-handling capacity from 12 million to 17 million tonnes has yet to be installed.