There are few industrial businesses that eat more electricity than making aluminium. And there are few countries with more electricity going to waste than Pakistan.

Put those two facts together and you have the logic behind the Hub Power Company’s (HUBCO) latest bet.

On November 16, HUBCO told the Pakistan Stock Exchange (PSX) that Hub Power Holdings Limited (HPHL), its wholly owned subsidiary, had hired a Chinese design institute to carry out a bankable feasibility study for an aluminium smelter. The proposed plant would produce 300,000 tonnes a year.

The company has not disclosed an investment figure or a timeline. Any decision to build depends on the study, on approvals and on financing.

Our view is simple. On paper, this is one of the more sensible ideas Corporate Pakistan has produced in years. Whether it works depends almost entirely on one number, the price HUBCO pays for its electricity.

How aluminium is made

Before we get to the economics, let us examine what a smelter does, and why it needs so much power.

Aluminium never occurs as a metal in nature. It is locked up in bauxite, bonded tightly to oxygen, and getting it out takes two plants.

The first is a refinery, which dissolves bauxite in hot caustic soda and roasts the result into alumina, a white powder. It takes 4 to 6 tonnes of bauxite to make about 2 tonnes of alumina, enough for 1 tonne of aluminium, according to the Australian Aluminium Council. Most of the energy a refinery uses is heat from gas or coal.

The second is the smelter, and this is the part HUBCO wants to build. Alumina is dissolved in molten cryolite at around 950°C, in long rows of cells called pots. A huge direct current passes through each pot and tears the oxygen away, and liquid aluminium collects at the bottom.

The electricity is not a fuel that heats the process. The electricity is the process.

A city’s worth of power

According to the International Aluminium Institute (IAI), the average smelter in the world used 14,114 kilowatt-hours (kWh) of electricity to make one tonne of aluminium in 2021.

At that rate, 300,000 tonnes a year needs about 4.2 billion kWh. In other words, HUBCO would need about 480 megawatts (MW) every hour of every day.

That is about 3.3% of all the electricity Pakistan generated in FY25, which came to 127,159 gigawatt-hours (GWh), according to the National Electric Power Regulatory Authority (NEPRA).

This is why electricity makes up roughly 40% of the cost of making aluminium. The industry rule of thumb is that a new smelter needs a 10 to 20 year power contract at around $30 to $40 per megawatt-hour (MWh) to compete.

Paying for idle plants

Pakistan has built more power plants than it can use. Installed capacity reached 46,605 MW in FY25, while peak demand was just over 33,000 MW, according to NEPRA. In winter, demand falls to 12,000 to 13,000 MW, a senior energy ministry official told Dawn last year.

Most of those plants were built under take-or-pay contracts, so they are paid whether they run or not. According to NEPRA, 61% of the Rs2.94 trillion the power sector paid for electricity in FY25 went on capacity payments, the fixed charges owed regardless of output.

Rooftop solar is making it worse. Grid sales fell around 3.6% in FY25. Every unit that leaves the grid pushes the fixed cost onto the units that remain.

Since December 2025, industrial and agricultural consumers have been able to buy electricity above their past consumption at a discount under the incremental consumption package. That rate was Rs22.98 per kWh until this month, when NEPRA raised it to Rs25.30.

The number that matters

Here is the problem, though. At Rs25.30 per kWh and Rs276.65 to the dollar, the discounted rate works out to about $91 per MWh. That is more than double what a smelter can afford.

At that price, the electricity in a tonne of aluminium would cost about $1,290. Aluminium on the London Metal Exchange (LME) has traded at roughly $3,000 to $3,300 a tonne this month. Power alone would eat about 40% of the selling price.

At the old industrial rate of Rs34 per kWh, it would cost about $1,735 a tonne. A smelter at that price is not a business. It is a charity.

But consider what the electricity costs the system at the margin. NEPRA’s figures put the energy cost, the fuel and running cost of generating a unit, at an average of Rs9.0 per kWh in FY25. Capacity charges added another Rs14.3 per kWh, and those are paid whether the electricity is used or not.

Rs9.0 per kWh is about $32.5 per MWh, squarely inside the range a smelter needs. At that price, the electricity in a tonne of aluminium costs about $460.

In other words, the power Pakistan already pays for and does not use is, at its marginal cost, cheap enough to make aluminium with.

A smelter would add load around the clock, which is exactly the demand idle baseload plants need. Every extra unit sold spreads the fixed capacity payments a little thinner.

Why Hub, and why HUBCO

HUBCO is also unusually well placed. The power purchase agreement for its 1,292 MW oil-fired plant at Hub, in Balochistan, was cut short in October 2024, two and a half years early, as part of the government’s renegotiation with older independent power producers (IPPs).

That left a 1,100-acre coastal site with a jetty, water and transmission lines already in place. The company has said the old plant could serve as backup power.

What could go wrong

This view has its critics, who will argue, correctly, that Pakistan has a long history of granting special electricity prices and then reversing them. The incremental package expires in October 2028, and its rate has already been raised once.

A smelter takes years to build and decades to pay back. No lender will finance one on a three-year tariff. The feasibility study will only be as good as the power contract behind it, a price fixed for 10 to 20 years and tied to the marginal cost of surplus generation.

Is that a subsidy under another name? Not if the price covers the fuel cost of the extra units and something towards capacity. Anything above Rs9.0 a unit is money the system does not currently earn.

Pakistan has electricity it cannot sell, and HUBCO is offering to buy 4.2 billion units of it a year. Whether the government will sell at a price that works is the only question that matters.