If you read the headlines last week, you might think Pakistan had just found a gold mine. It did not. It found something much earlier and much less certain, and the difference is worth getting right.
Here is what was actually announced. On November 16, Lucky Cement told the Pakistan Stock Exchange (PSX) that National Resources (Private) Limited (NRL), a company in which it holds 33.33%, had identified copper and gold mineralisation across at least eight porphyry discoveries in Chagai, Balochistan.
NRL is owned by Lucky Cement, Fatima Fertilizer and Liberty Mills. It has drilled nearly 25,000 metres so far, and says it is working towards its first mineral resource estimate under international standards.
The numbers are genuinely encouraging. NRL’s chairman, Muhammad Ali Tabba, told the Pakistan Minerals Investment Forum that one drill hole hit 295 metres of continuous mineralisation grading 0.43% copper and 0.13 grams of gold per tonne, including 132 metres at 0.83% copper.
The new finds sit across 5.6 square kilometres at Darigwan, next to Tang Kaur, the deposit NRL first announced in April 2025.
The pace has been quick. NRL was granted its licence in October 2023. By April 2025 it had drilled 13 holes covering 3,517 metres, and the first six returned copper grades of 0.23% to 0.48%. Nineteen months later, the total drilled is roughly seven times that.
The company now holds five exploration licences in Balochistan, two for copper and gold, one for lead and zinc and two for antimony.
Our contention is simple. This is good news, and NRL deserves credit for it. But a drill hole is not a mine, the geology is the easy part, and on any reasonable timeline the first tonne of copper from Darigwan is more than a decade away, and quite possibly closer to two.
Mineralisation is not a mine
Let us get one thing straight about the vocabulary, because it matters.
Mineralisation means the metal is there. A mineral resource estimate is a formal, audited calculation of how much is there, to what level of confidence. A reserve is the part of that resource that can be mined at a profit, which requires a feasibility study, a mine plan and a price assumption.
NRL is at the first of these stages, heading towards the second. Every step after that takes years.
How long a mine takes
According to the International Energy Agency (IEA), major mines that came online between 2010 and 2019 took more than 16 years on average to get from discovery to first production. More than 12 of those years went on exploration and feasibility studies, and four to five on construction.
S&P Global Market Intelligence found the same thing in a study published in July. Across 232 assets, the average lead time from discovery to production was 16 years. For the 203 mines already operating, it was 14 years.
For projects that have completed feasibility studies but are still not producing, the average has stretched to nearly 30 years, mostly because of permitting delays.
In other words, Tang Kaur, announced in 2025, would on the global average start producing around 2041. And Pakistan is not an average country for this sort of thing.
The other Chagai mine
Here is the problem, though. The best guide to how long a Chagai copper mine takes is the other Chagai copper mine.
Reko Diq’s story began in 1993, when BHP signed an exploration joint venture with the Balochistan government. Tethyan Copper Company completed a bankable feasibility study in 2010 and applied for a mining lease in February 2011. The provincial government rejected the application that November.
What followed was eight years of litigation, a $5.9 billion arbitration award against Pakistan in 2019, and a fresh deal with Barrick in 2022. Early construction works started in 2025, with first production targeted for the end of 2028.
That target is now in doubt. In April, Barrick said it was slowing development, extending its review of the project to mid-2027, and warned of significant increases to the budget and the timeline.
If Reko Diq produces in 2028, it will have taken 35 years. None of that delay was geology. The copper was always there.
And the prize is not small. Phase 1 of the project is designed to produce up to 240,000 tonnes of copper a year, from a mine expected to run for at least 37 years. Every year of delay is a year of that output Pakistan does not get.
What NRL has going for it
To be fair to NRL, it is not starting where Reko Diq did.
It is owned by three of Pakistan’s largest business groups, not a foreign company negotiating with a provincial government. Its owners have committed $100 million to exploration, and Lucky Cement’s board recommended up to Rs1.2 billion more of equity in August 2025 to fund pre-feasibility work. Lucky Cement has said it will keep the exchange informed of further developments.
Its technical workforce is almost entirely Pakistani, and through its new Chagai Foundation it is supporting education in the district. Nor is it alone in the district. Ivanhoe Mines has since signed an agreement with Mari Minerals to explore for copper and gold in Chagai. And the grades compare reasonably with Reko Diq, whose reserves average 0.48% copper, though an intercept from one hole is not the same thing as the average grade of a whole deposit.
The questions that matter
The questions that will decide how fast this goes are not geological. They are the ones that stalled Reko Diq.
Will the mining lease come through on time and survive a change of government? Can a company of this size raise the billions of dollars a mine needs? And will security in Balochistan allow construction at all, when it has already slowed Barrick?
The first mineral resource estimate will tell us how much copper NRL has found. Everything after that will tell us how serious Pakistan is about mining it.