Construction of the 765-kilovolt transmission line from Dasu Hydropower Plant to Mansehra is facing delays due to outstanding payments, design disputes and land clearance issues, with the contractor claiming that 215 of the project's 420 tower locations remain affected by right-of-way and regulatory restrictions,
Business Recorder
reported.
In a letter dated November 2, 2026, to the managing director of the National Grid Company (NGC), Sinohydro Corporation Limited sought immediate intervention, claiming that approximately Rs1.494 billion and $146.677 million were outstanding against various invoices.
According to the contractor, 17 invoices under Schedule-4 worth Rs555.721 million remain pending, including Rs152.989 million in overdue payments. A separate invoice of $146.677 million is also outstanding, alongside overdue price adjustment claims of Rs272.897 million and customs-duty invoices worth Rs154.235 million.
Sinohydro also disputed a proposed payment mechanism linking compensation for completed access roads to the completion of tower foundations, erection and stringing. The company maintained that these were separate contractual activities and warned that continued non-payment could lead to suspension or reduction of work.
The contractor further reported Rs151.711 million in crop compensation claims awaiting submission for reimbursement because the employer had not regularly provided the required vouchers.
Three pending change orders were also identified, including Rs54.726 million for bridge strengthening near Tower No. 27, Rs709.909 million for foundation modifications covering 71 towers and CNY1.346 million for terminal towers to be imported from China. These approvals have reportedly been pending for more than ten, eight and four months, respectively.
Design-related problems are affecting more than 100 tower locations, with Sinohydro claiming that the original tower configurations failed to meet required clearance standards. The company said it had proposed special tower designs in 2023, but the employer acknowledged their necessity only in October 2026.
Other technical issues include repeated revisions to foundation designs, unresolved soil investigations and problems with the transmission-line alignment, which passes through steep terrain and crosses existing power lines. The contractor also cited the need for route modifications to account for future hydropower developments.
Right-of-way restrictions and pending forest clearances are reportedly affecting 123 tower locations in Section-I and 65 in Section-II, while another 27 locations await National Highway Authority approvals.
Sinohydro said no construction sites were available between Tower Nos. 150 and 198 because of unresolved right-of-way issues associated with the Besham Committee, disrupting the planned deployment of manpower and machinery.
The contractor has requested NGC to resolve the payment disputes, approve pending design changes and secure the necessary land and regulatory clearances. It warned that continued delays could result in claims for extensions of time and additional costs under the contract.
The 765-kV transmission line is intended to evacuate electricity from the Dasu Hydropower Project and strengthen Pakistan's national transmission network.