Image for: WB financing power projects worth $1.54bn in Pakistan; several schemes face delays

 

By Ijaz Kakakhel


ISLAMABAD, Nov 06 (INP-Wealth Pakistan) -- The World Bank is financing a series of projects across Pakistan's power sector, including transmission networks, cross-border electricity trade and improvements to electricity distribution and grid infrastructure, according to a project status document available with Wealth Pakistan.


The document lists nine financing entries worth a combined $1.54 billion, of which about $829.5 million has been disbursed.


Implementation progress varies, with several projects nearing completion while others face significant delays.


The largest allocation, $700 million, is for the transmission component of the Dasu Hydropower Project, intended to evacuate electricity from the 2,160-megawatt Dasu facility under Stage I. 


The document records disbursements of $343.3 million, financial progress of 67 percent and physical progress of 55 percent. It identifies serious right-of-way difficulties across eight districts as a major obstacle. The listed loan closing date is December 2028.


Another $425 million supports Phase I of the National Transmission Modernization Project. The package covers grid upgrades, expansion of transformation capacity, enterprise resource planning and the Islamabad West Grid Station. Disbursements under the modernization package stand at $255 million, the sheet shows. Security problems in Loralai and Sibi have also affected transmission upgrades, highlighting risks beyond financing and engineering capacity.


Progress is uneven across these components. The transmission interconnection work shows 98 percent physical progress, while transmission capacity improvements have reached 97 percent. The enterprise resource planning component is at 85 percent, with a planned go-live date of December 2026.


In contrast, the 765/500/220/132-kilovolt Islamabad West Grid Station has achieved only 38 percent physical progress, with delays attributed to tendering complications linked to new technologies.


The document also highlights the CASA-1000 project, designed to transmit electricity from Tajikistan and neighboring Central Asian sources to Pakistan. Its two separate World Bank financing entries total approximately $169 million, with $157.31 million disbursed. Both components report 96 percent physical progress, but full-system testing has been delayed because of the unavailability of the transmission line in Afghanistan.


Distribution reforms account for another major area of financing. Under the Electricity Distribution Efficiency Improvement Project, $73.44 million is allocated to PESCO, $58.12 million to MEPCO, $50.65 million to HESCO and $20.43 million to a Power Division component.


The document describes these four components as on track, despite modest reported physical progress of 22 percent for PESCO, 20 percent for MEPCO and 25 percent for HESCO. Their loans are scheduled to close in December 2027. The respective disbursements for PESCO, MEPCO and HESCO are $13 million, $6.78 million and $10.09 million.


Meanwhile, the $48 million Tarbela Fifth Extension power evacuation project has reached 93 percent in both financial and physical progress, with $40.7 million disbursed. Right-of-way disputes and court cases remain outstanding concerns.


A separate initiative to install reactive power compensation devices is still in the planning phase.


Taken together, the projects demonstrate the breadth of World Bank support for Pakistan’s electricity infrastructure, while underscoring persistent implementation challenges including land access, security concerns, procurement delays and cross-border dependencies.