By Abdul Ghani
ISLAMABAD, Nov 04 (INP-Wealth Pakistan) -- Work on the Housing Scheme Kuchlak Road, Quetta, is progressing steadily, with 161 housing units completed up to the first floor and another 417 grey-structure units completed up to the ground floor level.
According to an official document available with Wealth Pakistan, the latest package-wise progress shows that 136 houses have reached the substantial completion stage.
The project comprises four housing packages executed by M/S F.K. & Builders, covering 714 houses across various categories. Physical progress on these packages ranges from 44 to 71 percent, while financial progress stands between 40 and 61 percent.
The first package, comprising 150 housing units, has achieved 71 percent physical progress, while the second package, covering 129 houses, has recorded 57 percent progress. The third package, involving 196 units, has reached 47 percent physical progress, and the fourth package, comprising 239 units, has recorded 44 percent progress.
Apartment construction is also advancing under the scheme. Structurally, 20 blocks comprising 240 flats are complete, with finishing work underway. Structural work is also progressing on another 15 blocks comprising 180 flats.
Meanwhile, road construction, boundary-wall development and sewerage works under the infrastructure description are progressing under a separate Rs1.366 billion package.
The report further states that formal agreements for re-tendered contracts covering 96 three-bedroom flats and 120 three-bedroom flats are being processed.
The completion date for the four house-construction packages, the apartment packages with ongoing structural work, and the infrastructure package is set for December 30, 2027.