Image for: Pakistan pursues Rs2.985tr water and hydropower projects

 

By Ijaz Kakakhel


ISLAMABAD, Oct 15 (INP-Wealth Pakistan) -- The Water Resources Division is pursuing 13 major foreign-aided hydropower and water-related development projects worth Rs2.985 trillion, as Pakistan intensifies efforts to meet its growing water and energy requirements.


According to the Public Sector Development Program (PSDP) 2026-27, a copy of which is available with Wealth Pakistan, the government has allocated a total of Rs65.18 billion for these projects, including Rs51.45 billion in rupee cover.


The projects include the construction of major dams, the expansion and rehabilitation of hydropower stations, the development of irrigation systems, and improved flood management infrastructure. Their cumulative expenditure was estimated at Rs1.129 trillion as of June 30, 2026.


Among the major initiatives, the Dasu Hydropower Project (Stage-I) in Kohistan, Khyber Pakhtunkhwa, carries the highest approved cost of Rs1.738 trillion. The government has allocated Rs15 billion for the project during 2026-27, while cumulative expenditure has reached Rs472.90 billion. Its physical progress stands at 27%.


The Diamer Basha Dam Project, including the Tangir Hydropower component, is another major initiative. The project has an approved cost of Rs479.69 billion, with Rs10.01 billion allocated for the current financial year. Cumulative expenditure has reached Rs209.72 billion, while physical progress stands at 47%.


Similarly, the 800-megawatt Mohmand Dam Hydropower Project has been allocated Rs22 billion against its approved cost of Rs309.56 billion. The project has recorded cumulative expenditure of Rs223.75 billion, with physical progress reaching 81%. Besides generating electricity, the dam is expected to contribute to water storage, irrigation development, and flood management.


The allocations for these three major projects collectively account for Rs47.01 billion, representing approximately 72% of the total allocation for the 13 foreign-assisted schemes.


Alongside new dam construction, the government is upgrading existing hydropower facilities to improve generation capacity and operational efficiency.
The 1,410MW Tarbela Fifth Extension Hydropower Project has received Rs3.4 billion. Similarly, Rs1.48 billion has been allocated for the refurbishment and upgradation of Mangla Power Station to increase the generation capacity from 1,000MW to 1,310MW.


The other schemes include the rehabilitation of the Dargai Hydroelectric Power Station, with an allocation of Rs2.06 billion, and the second rehabilitation of the Warsak Hydroelectric Power Station, which has received Rs2.28 billion.


The 34.5MW Harpo Hydropower Project has been allocated Rs2.7 billion, and the Chitral Hydel Power Station Rs736 million to increase its capacity from 1MW to 5MW.


In addition to electricity generation, foreign-assisted investments are supporting water conservation and irrigation infrastructure.


The Naulong Multipurpose Dam Project has received Rs903 million, and the Kaitu Irrigation and Power Project under the Kurram Tangi Dam initiative has received Rs100 million.


Flood protection remains another important component of the development programme. The government has allocated Rs1.5 billion for the Flood Protection Sector Project-III and Rs3 billion for the Flood Management Enhancement Project in the Indus Basin.


The successful implementation of these projects is expected to enhance reservoir capacity, support agricultural productivity, and contribute to the country's long-term energy and water resource management objectives.