By Ayesha Saba
ISLAMABAD, Aug 25 (INP-Wealth Pakistan) – Khyber Pakhtunkhwa’s World Bank-assisted Rural Accessibility Project has edged ahead of schedule, achieving 71% physical progress against a 70% target, as work on roads, bridges and transport facilities for schoolgirls continues across the province.
According to a document available with Wealth Pakistan, the project has also reached 54% financial progress. Under Component-I, which focuses on improving rural accessibility through roads and bridges, the approved scope covers 877.86 kilometres of roads and 16 bridges. Of these, 400 kilometres of roads and five bridges have been completed.
The document shows that the component has an approved budget of Rs96,786 million, while Rs49,268 million has been disbursed to date.
The project is designed to improve rural access to markets, education and health facilities through infrastructure upgrades and better transport services.
Its second component, aimed at providing safe and affordable school journeys for girls, has also recorded substantial activity. Transport services have been launched in 162 schools, benefiting 15,419 students.
The programme for middle-school girls in classes 6 to 9 has been implemented in seven districts, following surveys conducted in nine districts — D.I. Khan, Lakki Marwat, Hangu, Torghar, Kolai Palas, Kohistan Lower, Kohat, Charsadda and Bannu.
The total budget allocated for the school transport component stands at Rs3,773 million.
Under Component III, a construction supervision consultancy for civil works contracts and site activities is in the implementation phase with an allocated budget of Rs3,900 million.
A firm, Khwendo Kor, has also been engaged to support prevention and response services related to gender-based violence, sexual exploitation and abuse and sexual harassment risks, with Rs95 million allocated for the activity.
The project is additionally moving ahead with consultancy work for a bridge management system and road asset management system to strengthen the communication and works department, backed by an allocated budget of Rs450 million.
An impact assessment consultancy for Component II has been onboarded with an allocation of Rs150 million. At the same time, the third-party design review for Component-I has been completed with an allocated budget of Rs55 million.
The financial position up to June 2026 shows cumulative releases of Rs60,382 million against cumulative expenditure of Rs52,857 million, leaving a progressive balance of Rs7,524 million.
The project’s original PC-I, amounting to Rs69.44 billion, was approved by the Executive Committee of the National Economic Council on May 31, 2023. The Central Development Working Party later recommended a revised PC-I on March 21, 2025, and ECNEC approved it on May 14, 2025, at Rs112.86 billion.
According to the project cost-sharing arrangement, the World Bank accounts for 93.81% of the financing, equivalent to Rs105,840 million, while the government of Khyber Pakhtunkhwa contributes 6.19%, or Rs6,986 million. The cost-sharing table puts the total at Rs112,826 million.
The loan agreement was signed on November 1, 2022, while the communication and works department is the implementing agency. The project is scheduled to close on June 30, 2027.