By Ayesha Saba
ISLAMABAD, Aug. 20 (INP-Wealth Pakistan) -- Pakistan aims to complete the privatisation of three power distribution companies (DISCOs) by January 2027, with the transaction for Faisalabad Electric Supply Company (FESCO) currently at the most advanced stage.
The timeline in documents from the Ministry of Privatisation, available with Wealth Pakistan, shows that the process will now proceed through prequalification, buy-side due diligence, bid submission, and results approval before contracts are signed for the three Batch-I distribution companies.
According to the documents, the Privatisation Commission has received 12 Expressions of Interest (EOIs) for FESCO’s privatisation, comprising three investors from Türkiye, one from China and eight from Pakistan, while prequalification of interested parties is in process.
Under the indicative schedule, the prequalification of bidders for FESCO is targeted for completion by the end of August, followed by the completion of buy-side due diligence by the end of November. Bid submissions and the approval of results are targeted for mid-December, paving the way for contract signing in early January 2027.
The process for Gujranwala Electric Power Company (GEPCO) is following closely behind. Its deadline for submission of EOIs, Statements of Qualification (SOQs), and Non-Disclosure Agreements (NDAs) is August 21, 2026.
Prequalification and onboarding of qualified GEPCO bidders to the virtual data room are targeted for mid-September, while buy-side due diligence is scheduled for completion by mid-December. Bid submission and results approval are envisaged by the end of December, followed by contract signing in mid-January 2027.
Islamabad Electric Supply Company (IESCO), the third company in Batch-I, has a September 7 deadline for the submission of EOIs, SOQs and NDAs. Its bidder prequalification is targeted for completion by the end of September and buy-side due diligence by the end of December.
According to the transaction schedule, IESCO's bid submission and results approval are targeted for mid-January 2027, with the contract expected to be signed by the end of January.
The three companies are being offered an approved transaction structure allowing an outright sale of 51 to 100 percent of the share capital together with management control.
The structure also allows prospective bidders to compete for multiple Batch-I DISCOs, although eventual ownership or shareholding will be limited to only one of the three companies.
The privatisation process traces back to the government's Privatisation Programme 2024-29, under which FESCO, GEPCO and IESCO were grouped as Batch-I DISCOs. The Privatisation Commission Board had declared their divestment a major privatisation initiative and authorised the appointment of a financial adviser.
Following a competitive process, a consortium led by Alvarez & Marsal Middle East Limited, Dubai, UAE, was appointed the financial adviser on February 11, 2025.
The adviser has since completed the sell-side due diligence covering the sector, company, legal and regulatory, financial and tax, environmental and safety, and human resource aspects, besides preparing the transaction structure and restructuring plan.