By Ayesha Saba
ISLAMABAD, Aug. 12 (INP-Wealth Pakistan) -- Five road packages in Dera Ismail Khan have reached 12 to 28 per cent physical progress under the Asian Development Bank-supported Khyber Pakhtunkhwa Rural Roads Development Project, advancing the province’s Rs105.45 billion rural connectivity programme.
According to the project documents available with Wealth Pakistan, Package-2 (Lot-2) has recorded the highest physical progress at 28 per cent. The package carries an AA (administrative approval) cost of Rs3.17 billion against a bid cost of Rs4.10 billion, while progressive expenditure stands at Rs1.3 billion. Work on the package commenced on December 1, 2025.
Package-2 (Lot-3) has reached 18 per cent physical progress. Its AA cost is Rs1.53 billion against a bid cost of Rs1.74 billion. The project, which also began on December 1, 2025, has progressive expenditure of Rs456 million.
Package-1 (Lot-2) has achieved 21 per cent physical progress. It has an AA cost of Rs2.42 billion against a bid cost of Rs3.25 billion, while progressive expenditure stands at Rs807 million. The package also commenced on December 1, 2025.
The document shows that Package-2 (Lot-1) has recorded 12 per cent physical progress. The package carries an AA cost of Rs3.54 billion and a bid cost of Rs5.12 billion, with progressive expenditure of Rs551 million. Its commencement date was December 10, 2025.
Package-1 (Lot-1) has achieved five per cent physical progress. It has an AA cost of Rs6.36 billion against a bid cost of Rs8.4 billion, while progressive expenditure stands at Rs1.17 billion. Work on the project commenced on December 12, 2025.
The document further says that DI Khan forms part of the wider Khyber Pakhtunkhwa Rural Roads Development Project, which envisages the improvement of 92 roads with a combined length of 980.9 kilometres across 18 districts.
The programme covers 37 rural access roads spanning 324.4km, 36 flood-affected roads covering 474.2km and 19 tourism roads extending 182.3km. It also provides for 34 bridges, comprising 15 reinforced cement concrete (RCC) and 19 steel bridges.
The project carries a total cost of Rs105.45 billion. The Asian Development Bank's share amounts to Rs91.2 billion, or 86.5 per cent, while the Khyber Pakhtunkhwa government is contributing Rs14.249 billion, equivalent to 13.5 per cent.
The project aims to improve rural access to markets, education, and health facilities through infrastructure upgrades and improved transport services. It is scheduled to close on November 25, 2029.