By Ayesha Saba
ISLAMABAD, Aug 11 (INP-Wealth Pakistan) – World Bank-supported agriculture, tourism and transport projects in Khyber Pakhtunkhwa are slated for completion by 2026-27, while rural development and economic corridor schemes are expected to be completed by 2029.
According to a document available with Wealth Pakistan, the $171 million KP Integrated Agriculture Improvement Project has achieved 80% physical progress, with $156.1 million already disbursed. The project, being executed by the agriculture department, is scheduled for completion in December 2026.
The document said the project had faced delayed approval of a revised PC-I related to the implementation modalities of the High Efficiency Irrigation Systems (HEIS). However, the Executive Committee of the National Economic Council approved it on May 21, 2026.
Meanwhile, progress on the $100 million KP Integrated Tourism Development Project stands at 80% for the tourism component and 70% for the communication and works component, with total disbursement reaching $74.40 million.
The project completion date has been revised to April 30, 2027, against the earlier June 30, 2026 timeline.
Some implementation bottlenecks, however, remain. Work on the 22-kilometre Mankiyal road has remained suspended since October 2025 because of unresolved land acquisition and pending approval of land rates. Completion of the Thandiani Road, meanwhile, depends on timely relocation of utilities and a no-objection certificate from the forest department.
In the transport connectivity sector, the $378 million KP Rural Accessibility Project has achieved 61% physical progress, with $216 million having been disbursed. The C&W department-led project, signed in November 2022, is scheduled to be completed by June 30, 2027. The document identified delayed release of funds by the KP government as an implementation issue.
The $200 million KP Rural Investment and Institutional Support Project will be completed in June 2029, as disbursements have reached $45.1 million.
Agriculture activities under this programme have recorded 28% physical progress, while the C&W, public health engineering, local government and irrigation components have shown zero physical progress at the reporting stage. Preparatory work, however, is underway across several components.
The project's monitoring and evaluation firm has been brought on board, its results framework finalised and grievance redress mechanisms established. Contracts for four tehsil complexes have also been awarded, with work having commenced at Landi Kotal and Khar. Two district complexes are undergoing re-bidding, and nine additional schemes are at the procurement preparation or review stages.
The $460.6 million Khyber Pass Economic Corridor project is to be completed in May 2029. The document also identifies a $75 million KP component. Physical progress on Component-II under the provincial C&W department stands at 15%, and $4.4 million has been disbursed so far.
The project has already seen completion of the Greater Peshawar Development Plan and urban master plans for Jamrud and Landi Kotal subdivisions. An inclusive business development park has been established and is hosting 20 SMEs, while enterprise development skills training has been completed for 503 beneficiaries.
The remaining issue highlighted in the document is finalisation of the alignment and detailed design of the Peshawar-Torkham Expressway by the National Highway Authority, as earlier alignment revisions affected the proposed locations of key investments. The Ministry of Economic Affairs has requested the Ministry of Communications/NHA to expedite finalisation of the design and approval of the PC-I.