By Abdul Ghani
ISLAMABAD, Aug 11 (INP-Wealth Pakistan) -- The Sindh government's Rs50.99 billion Kalri Baghar Feeder Upper Phase-I canal lining project has created an estimated 83,300 acre-feet of additional water storage at Keenjhar Lake, significantly improving Karachi's water security during peak summer, according to documents available with Wealth Pakistan.
The documents reveal that as of June 2, 2026, the lake's water level reached 49.40 feet, the highest level recorded for that date, due to reduced seepage from the completed sections of the canal lining project.
The project, approved by the Executive Committee of the National Economic Council (ECNEC) in July 2023, aims to line 57.81 kilometres of the Kalri Baghar Feeder Upper canal with cement concrete to eliminate water losses and improve conveyance efficiency. So far, 42.08 kilometres of canal lining have been completed, representing 78 percent of the total target.
Official records show that financial progress has also reached 78 percent, with Rs31.54 billion released and spent on the project. The revised project cost stands at Rs50.99 billion, up from the original approval of Rs39.94 billion, with implementation continuing until 2026-27.
The Irrigation Department estimates that once completed, the project will eliminate 510 cusecs of seepage losses, enabling the conserved water to help meet the 260 million gallons per day (MGD) demand under the K-IV Phase-I water supply scheme through Keenjhar Lake. The initiative is expected to strengthen Karachi's long-term water supply while improving irrigation efficiency across Sindh.
According to the documents, work under Package-2 has reached 96 percent completion, while Package-1 and Package-3 stand at 56 percent and 70 percent, respectively. Overall, only 15.73 kilometres of canal lining remains to be completed.
The project also includes supporting infrastructure, with a five-barrel super-passage at RD-90 (reduced distance) already functional, a prestressed bridge at RD-151 targeted for completion by the end of August 2026, and bank protection works along the tail reaches nearing completion.
The Irrigation Department maintains that both physical and financial progress are fully aligned and that the project remains on schedule for completion within the approved implementation period from 2023-24 to 2026-27.