By Ayesha Saba

 

ISLAMABAD, Aug 11 (INP-Wealth Pakistan) – The Khyber Pakhtunkhwa government has spent Rs12.984 billion so far on the rehabilitation of flood-hit irrigation channels, drainage systems and flood-protection structures across the province against an allocation of Rs15 billion.

 

Documents concerning the Asian Development Bank-backed Emergency Flood Assistance Project, a copy of which is available with Wealth Pakistan, show that the initiative covers 143 works, including 79 irrigation, headworks and drainage schemes and 64 flood-protection works.

 

The project scope includes the rehabilitation of 91.40 kilometres of irrigation channels, 262km of drains and flood-carrier channels, and 67.90km of flood-protection works.

 

The Irrigation Department is implementing the project across Swat, Malakand, Charsadda, Nowshera, Peshawar, Dir, Chitral, Bannu and Dera Ismail Khan.

 

The financial table places the foreign-funded component at Rs13.2 billion, against which cumulative expenditure has reached Rs12.693 billion. The local component is valued at Rs1.8 billion, with expenditure recorded at Rs291 million.

 

Together, the two components bring the project cost to Rs15 billion and cumulative spending to Rs12.984 billion, reflecting substantial utilisation of the available financing.

 

The distribution of works shows that the Dera Ismail Khan circle has the largest number of irrigation, headworks and drainage interventions at 66, while no separate flood-protection work is listed for the circle.

 

Swat has the largest combined portfolio after Dera Ismail Khan, with 38 works, comprising seven irrigation, headworks and drainage schemes and 31 flood-protection works.

 

The Peshawar circle has 16 works, including five irrigation, headworks and drainage schemes and 11 flood-protection works. Swabi has 11 works, comprising one irrigation-related scheme and 10 flood-protection interventions.

 

The Mardan circle has 10 flood-protection works, while Bannu has two such works. In total, the project portfolio consists of 79 irrigation, headworks and drainage interventions and 64 flood-protection works.

 

The loan agreement for the project was signed on December 15, 2022, and became effective on February 9, 2023. Its design stage ran from April to December 2023.

 

The original loan closing date of June 30, 2026, has been revised to June 30, 2027, providing additional time for the completion of the reconstruction and rehabilitation programme.

 

Under ADB Loan No. 4279-PAK, the overall loan amount is $475 million, of which Khyber Pakhtunkhwa’s portion is $59.1 million.

 

The financing carries a repayment period of 30 years, including a grace period of 10 years. Interest has been set at one percent per annum during the grace period and thereafter on the amount withdrawn and outstanding from time to time.

 

The documents also record $3.37 million in capitalised interest, financed under the loan and attributable to the overall ADB financing of $475 million.

 

With spending approaching Rs13 billion and work spread across irrigation, drainage and flood-protection infrastructure, the programme is strengthening the province’s capacity to restore flood-damaged assets and protect vulnerable areas from future water-related risks.