By Ijaz Kakakhel

 

ISLAMABAD, Aug 11 (INP-Wealth Pakistan) -- The funding impasse delaying the Greater Karachi Bulk Water Supply Scheme (K-IV) has been resolved, paving the way for the completion of Phase I by December 2026, according to an official brief submitted to the National Assembly and available with Wealth Pakistan.

 

The project has achieved 69.5% physical progress, while cumulative expenditure has reached Rs94.65 billion. Work is continuing on all major components, including the intake structure, pumping stations, pressurised water-conveyance pipelines, reservoirs and filtration plants.

 

K-IV Phase-I is designed to supply 260 million gallons of water per day (MGD) to Karachi from Keenjhar Lake in Thatta district.

 

The bulk water will be delivered to Karachi through three termination points, including Pipri, the North-East Karachi (NEK) Pumping Station and Manghopir. The project is being implemented by the Water and Power Development Authority under eight contracts awarded to different local and international contractors.

 

According to the financial details, the project’s modified revised PC-I cost stands at Rs126.404 billion. A second revised PC-I, carrying an estimated cost of Rs171.814 billion, is currently awaiting approval.

 

The federal government allocated Rs15.112 billion to the project under the Public Sector Development Programme in 2021-22, followed by Rs20 billion in 2022-23, Rs21.329 billion in 2023-24 and Rs30 billion in 2024-25. Another Rs8.209 billion was allocated and released during 2025-26.

 

For 2026-27, an allocation of Rs10 billion has been provided against the project’s stated demand of Rs32.797 billion. Overall allocations have reached Rs104.65 billion, while actual releases total Rs94.65 billion. The latest funding arrangement is expected to allow construction activity to continue without the interruptions that previously affected progress.

 

Under the approved division of responsibilities, WAPDA is constructing an intake structure with a capacity of 650 MGD at Keenjhar Lake, along with a 650-MGD gravity channel leading to the Keenjhar pumping complex.

 

The pumping complex will contain two pumping stations, each with a capacity of 130 MGD. WAPDA is also responsible for the 260-MGD pressurised pipeline system, its associated structures, and three reservoirs and filtration plants.

 

The Sindh government is responsible for the distribution and augmentation system, a 50-megawatt power supply arrangement, land acquisition and clearance of the project’s right-of-way.

 

With the financial bottleneck addressed and nearly seven-tenths of construction completed, the authorities are now focusing on maintaining the pace of work and ensuring that the remaining funds are released on time to meet the December 2026 deadline.