By Abdul Ghani

 

ISLAMABAD, Aug 11 (INP-Wealth Pakistan) -- Balochistan has completed desilting over a four-kilometre stretch of the Pat Feeder Canal under the channel’s remodelling project to improve water flow and operational efficiency, according to a document available with Wealth Pakistan.

 

The document reveals that the Irrigation Department is making steady progress on Package-I of the Rs15.75 billion Pat Feeder Canal Remodelling Project, which has been awarded to M/s D. Baloch-Shahrukh JV at a contract cost of Rs15.75 billion.

 

In addition, concrete lining has been completed over a one-kilometre section, while canal banks have been prepared for 2.3 kilometres.

 

The project has entered another major construction phase, with canal diversion works currently underway along a seven-kilometre stretch.

 

Preparatory activities have largely been completed, including joint and pre-construction surveys, establishment of site accommodation facilities, operational laboratories, and issuance of engineering drawings for the project's main components.

 

The document further states that the land acquisition survey has been completed, while the award process for land acquisition is in progress. To facilitate construction, authorities have removed more than 200 houses built as encroachments within the canal's right-of-way.

 

The remodelling of the Pat Feeder Canal System aims to improve irrigation efficiency, reduce water losses, and ensure a more reliable water supply to farmlands across Balochistan. Once completed, the project is expected to strengthen agricultural productivity and support long-term water resource management in the province.