By Ayesha Saba
ISLAMABAD, July 30 (INP-Wealth Pakistan) -- Two major N-55 dualization packages have entered the final stretch, with physical progress reaching 82% on the Kashmore-Rojhan section and 79% on the Rojhan-Rajanpur section ahead of their scheduled completion dates in October 2026.
According to documents available with Wealth Pakistan, the 49km Kashmore-Rojhan section under CAREC Tranche-II is leading with 82% progress. The Rs7.035 billion contract, which commenced in August 2023, is scheduled for completion on October 20, 2026.
The adjoining 50.18km Rojhan-Rajanpur section under Lot-4 has recorded 79% physical progress. Work on the Rs7.576 billion package also commenced on August 17, 2023, and its scheduled completion date is October 25, 2026. ZKB is the contractor for both packages, while MINCONSULT Joint Venture serves as the consultant.
The two sections form part of the additional carriageway project from Shikarpur to Rajanpur on N-55 under CAREC Tranche-II. The documents state that the overall project length is 222km and that the approved PC-I cost is Rs44.704 billion.
The project has received Rs5 billion under the Public Sector Development Programme (PSDP) for 2026-27, comprising Rs4 billion in foreign funding and Rs1 billion in local funding.
Progress on the remaining two packages stands at comparatively earlier stages. The 62km Shikarpur-Kandhkot section under Lot-1 has achieved 34% physical progress.
The Lot-1 contract is valued at Rs8.848 billion. Work commenced on March 14, 2024, and is scheduled for completion on April 15, 2027. ZKB is executing the package, while MINCONSULT Joint Venture is providing consultancy services.
The 59km Kandhkot-Kashmore section under Lot-2 has recorded 22% physical progress. Its Rs11.276 billion contract commenced on March 13, 2024, and is scheduled for completion on April 16, 2027.
China Civil Engineering Construction Corporation is the contractor for Lot-2, with MINCONSULT Joint Venture serving as the consultant.
The four packages cover the Shikarpur-Kandhkot, Kandhkot-Kashmore, Kashmore-Rojhan and Rojhan-Rajanpur sections of N-55. Their individual lengths are listed as 62km, 59km, 49km and 50.18km, respectively. The Asian Development Bank is supporting CAREC Tranche-II through a $190 million loan under Loan No. 4099-PAK.
According to the documents, the loan became effective on March 18, 2022, and is scheduled to close on December 31, 2027.