By Ayesha Saba
ISLAMABAD, July 29 (INP-Wealth Pakistan) -- Construction has formally commenced on two N-55 packages worth Rs94.6 billion, with the 208-kilometre DG Khan-DI Khan corridor scheduled for completion by June 2028.
According to the documents available with Wealth Pakistan, the contracts covering the 112km DG Khan-Tibbi Qaisrani and 96km Tibbi Qaisrani-DI Khan sections were awarded on June 23, 2026, while work commenced on June 29.
Lot-3 involves the dualization and rehabilitation of the 112km DG Khan-Tibbi Qaisrani section of N-55. The contract, valued at Rs51.997 billion, has been awarded to a joint venture of Ningxia Communication Construction Company Limited and Dynamic Constructors.
Lot-4 covers the dualization and rehabilitation of the 96km Tibbi Qaisrani-DI Khan section. The Rs42.604 billion contract has been awarded to a joint venture of Ningxia Communication Construction Company Limited and Rustam Associates.
This package includes the 5.46km Ramak bypass. MINCONSULT joint venture is the consultant for both Lot-3 and Lot-4.
The two packages form part of the 330km Rajanpur-DG Khan-DI Khan corridor under CAREC Tranche-III, which covers the dualization and rehabilitation of the existing carriageway.
The corridor comprises two principal projects. The 121.5km Rajanpur-DG Khan stretch consists of the 58km Rajanpur-Jampur section under Lot-1 and the 64km Jampur-DG Khan section under Lot-2. The 208.19km DG Khan-DI Khan stretch comprises the 112km Lot-3 and 96km Lot-4.
The Rajanpur-DG Khan project has an approved PC-I cost of Rs63.151 billion. It has received Rs5 billion under the Public Sector Development Programme for 2026-27, including Rs4.5 billion in foreign funding and Rs500 million in local funding.
The DG Khan-DI Khan project carries an approved PC-I cost of Rs111.940 billion. Its PSDP allocation for 2026-27 also stands at Rs5 billion, comprising Rs4 billion in foreign funding and Rs1 billion in local funding.
For Lot-1, the 58km Rajanpur-Jampur section has a contract cost of Rs23.557 billion. Ningxia Communication Construction Company Limited and Rustam Associates joint venture is listed as the contractor, while the letter of award has yet to be issued.
The section includes three bypasses: Rajanpur at 10.64km, Fazil Pur at 8.58km and Muhammad Pur at 5.1km.
The Asian Development Bank loan for CAREC Tranche-III amounts to $360 million under Loan No. 4416-PAK. It became effective on March 13, 2024, and is scheduled to close on June 30, 2027.
For land acquisition along the corridor, expenditure to date stands at Rs7.4 billion, while Rs1.3 billion has been allocated under the PSDP for 2026-27. A rationalised PC-I amounting to Rs23.952 billion was approved by the NHA Executive Board on May 18, 2026.
The land plan provides a 33-metre right-of-way for the existing road and 100 metres for bypasses. It covers six bypasses totalling 62.99km between Rajanpur and DG Khan and five bypasses totalling 35.84km between DG Khan and DI Khan.