By Abdul Ghani


ISLAMABAD, July 23 (INP-Wealth Pakistan) -- The federal government is set to finance the expansion of natural gas infrastructure to 173 villages and towns in Sindh under the 6th, 7th and 8th year implementation plan of Sui Southern Gas Company (SSGC), with projects estimated to cost over Rs4.28 billion, according to the documents obtained by Wealth Pakistan.


The implementation plan shows that the proposed schemes will cover Sanghar, Shikarpur, Tando Mohammad Khan and Sujawal districts, where 505.81 kilometres of gas pipelines will be laid to provide gas to 6,611 prospective consumers.


During the 6th year (FY2026-27), the SSGC plans to execute two gasification schemes in Sanghar and Shikarpur, covering 46 villages. The projects include 178.82 kilometres of gas pipelines and are expected to benefit 2,710 prospective consumers. The estimated project cost is Rs1.495 billion, including Rs146.34 million as the SSGC share and Rs1.349 billion as the federal government's contribution.


For the 7th year (FY2027-28), four schemes are proposed in Sanghar and Tando Mohammad Khan, covering 67 villages. The projects involve 171.97 kilometres of gas pipelines and are expected to provide gas to 2,281 prospective consumers. The total estimated cost stands at Rs1.408 billion, of which Rs123.17 million will be borne by the SSGC and Rs1.284 billion by the federal government.


Similarly, the 8th year (FY2028-29) implementation plan envisages gasification of 60 villages in Sanghar, Sujawal and Shikarpur. The schemes include 155.02 kilometres of gas pipelines to benefit 1,620 prospective consumers. The total project cost has been estimated at Rs1.374 billion, comprising Rs87.48 million from the SSGC and Rs1.286 billion from the federal government.


The implementation plan notes that these schemes will proceed in future years, contingent upon the release of the federal government's share and the depletion profile of the respective gas-producing fields.


Overall, the 6th to 8th year program is expected to extend gas supply to 173 villages, lay 505.81 kilometres of pipelines and connect 6,611 new consumers at a cumulative cost of approximately Rs4.28 billion.