By Moaaz Manzoor


ISLAMABAD, July 23 (INP–Wealth Pakistan) -- The federal government has allocated Rs8 billion in the Public Sector Development Programme 2026-27 for three major road projects with a combined approved cost of Rs238.625 billion. The primary beneficiary is  the N-5 highway widening project, which received Rs6 billion.


According to an official PSDP document available with Wealth Pakistan, the three projects include the Jaglot-Skardu Road, the Shandur-Gilgit Road and the widening and improvement of 216 kilometres of the N-5’s priority sections.


Of the total Rs8 billion allocation, Rs3 billion will be provided through the rupee component, while Rs5 billion will come through foreign assistance.


The largest allocation has been earmarked for the N-5 improvement project, which has an approved PC-I cost of Rs155.408 billion. The project will receive Rs6 billion during FY2026-27, comprising Rs1 billion in local funding and Rs5 billion in foreign assistance.


The Asian Infrastructure Investment Bank-funded project covers 210 kilometres of the N-5 and has been divided into two phases.


Phase I-A includes the 70-kilometre Ranipur-Sukkur section, the 40-kilometre Rawalpindi-Hassanabdal section and the 31-kilometre Nowshera-Peshawar section.


Phase I-B covers the 68-kilometre Lahore-Gujranwala section and a one-kilometre New Nai Baran Bridge.


The project was approved by the Executive Committee of the National Economic Council in August 2025 and is targeted for completion by June 30, 2029.


Only Rs83.009 million had been spent on the project by June 2026, leaving a throw-forward requirement of Rs155.325 billion as of July 1, 2026. The document said the procurement process is expected to be finalised in November 2026.


The government has separately allocated Rs1 billion for the construction of the 216-kilometre Shandur-Gilgit Road.


The project, approved by ECNEC in June 2021, has a PC-I cost of Rs49.946 billion. Cumulative expenditure stood at Rs42.212 billion by June 2026, leaving a throw-forward of Rs7.734 billion.


The road is targeted for completion by July 31, 2027. According to the document, physical progress had reached 71% on Package-I, 69% on Package-II and 64% on Package-III.


Another Rs1 billion has been allocated for the revised improvement, upgradation and widening of the 167-kilometre Jaglot-Skardu Road.


The project carries an approved cost of Rs33.271 billion and had received cumulative expenditure of Rs28.129 billion by June 2026. Its remaining throw-forward stood at Rs5.142 billion.


The Jaglot-Skardu project was approved by ECNEC in September 2024. The document lists the project as completed, while its updated physical status is described as substantially completed.


Taken together, cumulative expenditure on the three projects reached Rs70.424 billion by June 2026, while their combined throw-forward stood at Rs168.201 billion at the beginning of FY2026-27.


The latest allocations place the N-5 improvement project at the centre of the government’s road-development programme, while providing additional funding to complete the remaining work on the two northern road links.