By Ayesha Saba


ISLAMABAD, July 22 (INP-Wealth Pakistan) -- All four packages of the 153-kilometre Chitral-Booni-Mastuj-Shandur Road are targeted for completion by December 2026, with physical progress reaching 47.54% on one section, according to a project document available with Wealth Pakistan.


The project requires an allocation of Rs4.20 billion for financial year 2026-27 as construction advances along the route connecting Chitral with Shandur through Pret, Booni, Mastuj and Shaidas.


The project, designated as National Highway N-140, has a PC-I cost of Rs17.78 billion. It was initiated after the route was federalised in May 2020 and divided into four construction packages.


According to the document, Rs6.59 billion has been spent on the project to date. Its annual allocation for 2025-26 stands at Rs1.50 billion, while an additional Rs5.50 billion was required during the year. 


The 38.965km first package, extending from Chitral to Pret in Lower Chitral district, is the most advanced, with 47.54% of construction completed since work began in November 2021.


The original contract cost of the package was Rs2.67 billion, subsequently revised to Rs2.74 billion. Its original completion date was November 2023, while the targeted completion date is December 2026.


The project document states that physical progress on the 39.723km second package, covering the Pret-Booni section in Lower Chitral, has reached 34.77% since work commenced in November 2021. The contract cost of the second package was revised down to Rs2.81 billion from the original Rs2.83 billion. Its original completion date was November 2023, while completion is now targeted for December 2026.


The third package covers 36.14km from Booni to Shaidas in Upper Chitral district. Physical progress on this stretch has reached 38.16%. Construction began in November 2021, and the contract cost was revised from Rs2.55 billion to Rs2.61 billion. The package’s original completion date was November 2023, while the revised target is December 2026.


The 37.782km fourth package runs from Shaidas to Shandur in Upper Chitral. Work on this section began in August 2022 and has achieved 29.78% physical progress.


Its original contract cost of Rs2.87 billion was revised to Rs2.93 billion. The original completion date was August 2024, while the new targeted completion date is December 2026.


Before the route was federalised, the 79km stretch from Chitral to Booni comprised a 3.65-metre-wide blacktopped road with one-metre shoulders on both sides. The 74km Booni-Shandur portion was a single-lane shingled track.


Following federalisation, the National Highway Authority initiated the improvement and widening of the route through four packages.