By Ayesha Saba
ISLAMABAD, July 22 (INP-Wealth Pakistan) -- The detailed design of the two sections of the 130.22-kilometre Chakdara-Chitral N-45 improvement project has been completed, while the technical evaluation of fresh bids for the third stretch has been submitted to the Korean EXIM Bank, according to documents available with Wealth Pakistan.
According to National Highway Authority (NHA) project documents, the N-45 improvement and widening project has been divided into three sections: the 38.85km Chakdara-Timergara stretch, the 43.39km Akhagram-Dir stretch and the 47.98km Kalkatak-Chitral stretch.
The documents show that Rs500 million has been allocated under the Public Sector Development Programme 2026-27 for Sections I and II, comprising Rs50 million in government funding and Rs450 million in foreign assistance. A separate Rs500 million allocation, with the same funding composition, has been provided for Section III.
The Chakdara-Timergara section is being designed as a 7.3-metre-wide carriageway with two-metre shoulders on each side and a design speed of 60 kilometres per hour.
A consortium of companies has been appointed to provide detailed design, procurement assistance and construction supervision services. The consultancy contract was signed in January 2025, followed by the issuance of the agreement in February.
The detailed design of the section has been completed, and a PC-I costing Rs17.012 billion was submitted to the Ministry of Planning, Development and Special Initiatives in March 2026. A $49.045 million loan for the section was signed in January 2021. The project completion and final disbursement dates are June and December 2028, respectively.
The 43.39km Akhagram-Dir section is covered by a $99.084 million loan signed in August 2024. The loan became effective in December 2024, while the project is scheduled for completion in December 2029.
Procurement of consultancy services had moved through shortlisting and bid evaluation. However, the Economic Development Cooperation Fund proposed in March 2026 that the appointment of Korean consultants be temporarily suspended in view of the situation between Pakistan and Afghanistan.
The document further said that the 47.98km Kalkatak-Chitral section has made further headway, with its detailed design already completed and fresh bids received from three joint ventures.
The section’s revised PC-I cost stands at Rs17.856 billion under the 2024 schedule of rates, compared with Rs10.951 billion under the 2022 schedule.
The initial procurement process was annulled after the only civil-works bid came in at Rs20.198 billion. The quoted amount was 224.24 per cent above the engineer’s 2022 estimate of Rs6.268 billion and 87.35% higher than the revised 2024 estimate of Rs10.848 billion.
Following the Korean EXIM Bank’s recommendation, the National Highway Authority launched a fresh bidding process. Three joint ventures submitted their bids in February 2026.
The technical evaluation report was sent to the Korean EXIM Bank in March. After receiving the bank’s observations, a revised report incorporating its comments was forwarded in April. A response from the bank is awaited.